Four Cranes Built in Less Than a Week

Installation & Runways

Installation of the cranes was also done by Excel Industries installation team. Job deadline was tight, but Excel beat the deadlines given by customers. All four cranes where built in less than a week. All cranes were installed on the same day, in one long working day.

Runways were built in less than three weeks, and all runways, were installed in less than two weeks. Runways consisted of two 10 ton free standing runways 100′ long each, and the one 50 ton free standing runway 585′ long. The cranes requested were two 10 ton cranes, 50′ span, and two 25 ton cranes, 55′ span.